ROYSTON CONCLUDES SERVICE WORK ON STENA DRILLING ENGINE

Importer
Royston has completed engine overhaul work onboard Stena Drilling's Stena DrillMax.

Conducted as part of logistical solution provided to the vessel’s owners and operators, a team of Royston engineers carried out a 48,000 running hours service on a Wartsila W16V32 engine in Las Palmas in the Canary Islands. The service was carried out within a tight timeframe despite the challenges posed by travel restrictions due to the pandemic.

The generator, one of six used to power thruster units as well provide electricity for operations, heating, power and lighting systems, received new fuel injectors, cylinder heads and liners as part of the service package, which involved the disassemble and rebuild of the power unit in an around the clock operation.

The initial programme of works was expanded following a primary inspection and additional Royston engineering resources were brought in to support the original team to complete work on the crankshaft seal replacement. Work on servicing the turbocharger was also completed and saw new cartridges and gaskets fitted to ensure optimum operational performance.

Royston engineers, who also oversaw engine testing in line with the manufacturer’s specification and tolerances, remained onboard the Stena DrillMAX to utilise planned downtime before it sailed to the coast of Guyana, South America, where it resumed drilling activities for an international oil exploration company. Completion of the contract follows other engine service work Royston has carried out on the Stena Drilling fleet.

Part of a six-strong fleet of vessels, the 228 metre long ‘Stena DrillMAX’ is a harsh environment dynamically positioned drill ship, designed for deep sea operations and capable of drilling in water depths up to 10,000 ft.